Jun 26, 2021 #1 CH Chattacuda Member Joined Apr 15, 2021 Messages 17 Location Tennessee I ordered a new 5.5kw LP generator from our local Cummins dealer yesterday. They were not optimistic about how long would take to get it in. They guessed 12 weeks. I guess we will find out eventually! Maybe before winter!
I ordered a new 5.5kw LP generator from our local Cummins dealer yesterday. They were not optimistic about how long would take to get it in. They guessed 12 weeks. I guess we will find out eventually! Maybe before winter!
Jun 27, 2021 #2 Ynot4me2 Senior Member Site Team Site Sponsor RV LIFE Pro Joined Mar 26, 2020 Messages 4,785 Location ON & QC Canada The shortage on a lot of stuff is crazy. Sent from my SM-P610 using Tapatalk
Aug 20, 2021 #3 OP OP CH Chattacuda Member Joined Apr 15, 2021 Messages 17 Location Tennessee They said 12 weeks at the Cummins sales place where i bought it. We were both pleasantly surprised when came in a little over 6 weeks later!
They said 12 weeks at the Cummins sales place where i bought it. We were both pleasantly surprised when came in a little over 6 weeks later!